Who This Checklist Is For
-
Step 1: Define the Real Load Before You Look at Generator Specs
-
Step 2: Choose the Correct Rating: Standby, Prime, or Continuous
-
Step 3: Compare Total Cost of Ownership, Not Just the Quote
-
Step 4: Check the Physical Installation Before You Commit to a Footprint
-
Step 5: Verify AHJ Compliance Requirements Before the Generator Ships
-
Step 6: Confirm the Service Network and Spare Parts Plan
-
Three Mistakes That Still Show Up on Job Sites
Who This Checklist Is For
At Perkins Generator, I've spent the past nine years working as a fuel generator distributor, mostly for Perkins-powered generator sets. In that time, I've personally made—and documented—14 significant mistakes, totaling roughly $38,000 in wasted budget. This checklist is what I use now to keep our team out of trouble. It's written for distributors, wholesalers, OEMs, and project-based buyers, not for homeowners doing a single install.
You can use it for a 22 kW home standby unit or for a 120 kW Perkins generator Florida project. The steps are the same. The order matters.
Step 1: Define the Real Load Before You Look at Generator Specs
From the outside, "120 kW" sounds like a simple number. The reality is that number only means something once you know the load profile. Is it a continuous load? A backup load that runs twice a week? Does it include a large motor that draws six times its running current for a few seconds?
On every quote, I ask for three things: the total running load in kW, the largest motor starting kVA, and the type of load (resistive, inductive, electronic). If the customer can't tell me, I send them a load sheet and I don't quote yet. That decision has saved more rework than any other check on this list.
In my first year (2017), I made the classic mistake. I quoted a 100 kW set for a pump station based on running amps. The pump's starting surge tripped the set on commissioning day. The replacement cost $4,200, plus freight for the next unit, plus a one-week delay. The larger set would have been about $3,000 more on day one.
That's total-cost thinking. The cheaper quote was the expensive one.
Step 2: Choose the Correct Rating: Standby, Prime, or Continuous
People assume kW is kW, but generator sets are rated differently depending on how long they run and how much load varies. Standby rating means the unit is sized for outages and won't be overloaded for long hours. Prime rating is for varying loads with unlimited hours. Continuous rating is for steady, non-varying loads around the clock.
What a lot of buyers don't realize is that the same Perkins engine and alternator package can be rated differently depending on the cooling package, enclosure, and control system. If a quote says "standby" but your customer plans to use the generator as a primary power source, you're setting up a call-back. If the quote says "continuous" but the set is really an off-the-shelf standby unit, the dealer may void the warranty.
Ask for the rating definition in writing. Every quote should state: standby kVA, prime kVA, continuous kVA, and the ambient temperature the rating is based on. If it doesn't, the quote isn't finished.
Step 3: Compare Total Cost of Ownership, Not Just the Quote
I used to compare quotes by the line at the bottom. Now I build a simple TCO sheet before comparing anything.
For a generator order, the line items I include are:
- Unit price
- Freight and rigging
- Installation materials: concrete pad, ventilation, exhaust, fuel supply
- Commissioning and load bank testing
- Automatic transfer switch and controls
- Spare parts and planned maintenance
- Downtime risk, which is hard to price but always real
On a 120 kW Perkins generator, the difference between a bare quote and a true ready-to-run quote can be huge. I've had plenty of projects where the lower-priced quote became the higher-priced project after adding the transfer switch, remote monitoring, and commissioning fee.
If a vendor tells you "that's extra," it's not a lie—but it's a red flag (sorry, but it really is). I'd rather get one complete number than a low number followed by a long surprise list.
Step 4: Check the Physical Installation Before You Commit to a Footprint
From the outside, measuring a generator is a quick exercise. The reality is that dimensions on a spec sheet don't tell you which side the exhaust exits, where the control panel opens, or whether the air intake is on the same side as the wall.
I once measured a generator that fit the room but not the door into the room. That mistake cost $1,100 in building modifications and made me look bad in front of a client I was trying to impress (not the kind of attention I wanted).
Before you issue a purchase order, verify these points:
- Access path: door height, corridor width, elevator capacity, crane reach.
- Service clearance: at least 3 feet on the control panel side, more on the alternator end if it needs servicing.
- Airflow: intake and exhaust must not recirculate hot air back into the radiator.
- Fuel: is there a day tank? Does the fuel return line exceed the engine's maximum allowable length?
This is where whole home generator compliance requirements start to overlap with installation planning. A compact residential unit placed close to a bedroom window might fail a noise code; a commercial unit placed near an air intake might fail local mechanical code. The manufacturer's installation manual gives minimum clearances, but the local building department is the one who decides what's allowed on site.
Step 5: Verify AHJ Compliance Requirements Before the Generator Ships
If I could redo my early career, I'd check the local authority having jurisdiction (AHJ) before I promised a delivery date. At the time, I thought compliance was a technical detail the contractor would handle. It isn't. It's a project killer.
The AHJ is the local building department, fire marshal, or other agency that has legal authority over the installation. They decide whether a permit is required, what drawings need to be submitted, and when inspections happen. The generator can be perfect and still sit on the truck because the permit wasn't approved.
For a 120 kW Perkins generator Florida commercial project, you might be dealing with wind load calculations, outdoor rated switchgear, fuel storage requirements, and noise limits. For a 22 kW whole home standby generator, the requirements are lighter but still real: an electrical permit, setback clearances, grounding, and sometimes a disconnect arrangement that meets local rules.
Here's something vendors won't always volunteer: if you're a home generator manufacturer, your install manual and marketing claims need to line up with reality. According to FTC business guidance on advertising (ftc.gov), claims must be truthful, not misleading, and substantiated. If you call something "whole home" coverage, you need to be able to support what that means in practice.
I once had a 12-unit order arrive at the loading dock before the electrical contractor had the permit in hand. The crane was rebooked, the crew was rescheduled, and the customer paid an extra $1,800 in waiting time. That number isn't on the generator spec sheet. It's a compliance cost.
Step 6: Confirm the Service Network and Spare Parts Plan
A Perkins engine isn't a disposable appliance. It has a service life measured in thousands of hours, but only if it gets the right filters, oil, and trained technicians. Before you commit to a genset, find out who supports it in the end-user's region.
The questions I ask are simple:
- Who is the authorized Perkins dealer closest to the installation site?
- What's the typical lead time for a fuel filter, an oil filter, and a starter?
- Does the dealer offer commissioning, or do I need a separate contractor?
- What spare parts should the end customer keep on site?
From a total cost perspective, a remote site may not need a lot of spare parts, but an unexpected two-week wait for a $40 sensor can idle a pump or a building that depends on backup power. The sensor costs nothing. The downtime costs everything.
If you're a distributor, treat this as a sales conversation, not a technical investigation. End customers buy confidence. Knowing the local support answer before you quote makes you look like a partner instead of a phone book.
Three Mistakes That Still Show Up on Job Sites
Even with a checklist, the same errors keep appearing. If you remember nothing else, remember these:
- Confusing kVA and kW. A generator rated in kVA at a 0.8 power factor is not the same as a unit rated in kW. Check the nameplate, then check the load.
- Ignoring altitude and temperature derates. A set rated at sea level and 25°C loses output at 3,000 feet or 40°C. An undersized set will fail exactly when it's needed most.
- Waiting until after the order to ask about compliance. The AHJ doesn't care how good the price was. They care whether the installation meets code.
The checklist approach isn't glamorous. It's just cheaper than the alternative. Looking back, I should have adopted it in my first year instead of after my third expensive mistake. If you're ordering Perkins generator sets for your customers, take this list, adjust it to your region, and use it before you send out that first purchase order.